Dated, Aizawl the 9th February, 2016
No. H. 13011/17/10-JERC: In exercise of powers conferred under Section 50 read with Clause (x) of Sub-section (2) of Section 181 of the Electricity Act, 2003 (36 of 2003), and all other powers enabling it in this behalf, the Joint Electricity Regulatory Commission for Manipur & Mizoram hereby makes the following Regulations to amend the Joint Electricity Regulatory Commission for Manipur & Mizoram (Electricity Supply Code) Regulations, 2013 (hereinafter referred to as “the Principal Regulations”), namely;
1. Short title and commencement
(1) This Regulations may be called the Joint Electricity Regulatory Commission for Manipur and Mizoram (Electricity Supply Code) (Third Amendment) Regulations, 2016.
(2) This Regulations shall extend to the whole States of Manipur and Mizoram and shall apply in relation to all matters falling within the jurisdiction of the Commission.
(3) This Regulations shall come into force from the date of their notifications in the Official Gazette of the concerned States.
2. Amendment in Regulation 4 of the Principal Regulations:
Clause 4.37(2) of the Principal Regulations shall be substituted as below:
(4.37) Charges for the above mentioned works to be paid by the applicant in accordance with the Estimate prepared by the Licensee on the basis of their approved Schedule rate/Store issue rate/Present market rate duly approved by the Commission as per Clause 4.117 of this Electricity Supply Code Regulations.
Provided that if the applicant wishes to carry out the works himself, he shall be permitted to do so under supervision by the licensee’s official. Adhering to the estimate and layout approved by the licensee, the applicant can get the work of drawing of service line from the licensee’s distribution mains up to his premises and the work of extension of HT/EHT line, Distribution or HT substation and LT line only through an eligible Licensed Electrical Contractor (LEC). In such case the consumer himself shall procure the materials. The material should conform to relevant BIS specifications or its equivalent and should bear the ISI mark wherever applicable. The licensee may ask for documentary evidence to verify the quality of materials used:
Provided further that if the applicant chooses to get the extension work done on his/her own, he shall bear only supervision charges as per the Estimate prepared by the Licensee on the basis of their approved Schedule rate/Store issue rate/Present market rate:
Provided further that if the applicant chooses to get the extension work done on his own, he shall get the work done within the timeframe specified in clause 4.41 of this Code, failing which the licensee may, on giving 15 days’ notice, treat the application form for supply as cancelled.
By Order of the Commission
Sd/- RICHARD ZOTHANKIMA
Assistant Secretary
Note: The Principal Regulations were notified in the Manipur Gazette Extraordinary, issue No. 349 dt. 15.1.2014 and in the Mizoram Gazette Extraordinary, Vol.-XLII, issue No. 642 dt. 20.12.2013. The First Amendment Regulations, 2014 were notified in the Manipur Gazette Extra Ordinary, issue No.217 dt 29.10.2014 and in the Mizoram Gazette Extra Ordinary, issue No. 506 dt 20.10.2014. The Second Amendment Regulations, 2015 were notified in the Manipur Gazette Extra Ordinary, issue No. 241 dt 12.6.2015 and in the Mizoram Gazette Extra Ordinary, issue No. 263 dt 12.6.2015.